St Pauls Catholic School, Thames Ditton

Duration

11 weeks

Value

£426k

The Project

We were appointed to design and install steel reinforcement to support failing RAAC planks at St Pauls Catholic School.

The works also included the isolation of all MEP services and their reinstatement following the repair works.

All steels were fire rated and dry packed in position.

We are delighted to say that the project completed two weeks early, allowing the staff and school children back into their classrooms ahead of schedule.

As an operational school it was critical that security and health & safety were strictly managed. Orion went above and beyond to ensure all procedures were in place and rigourously adhered to.

Another very successful project working alongside the school’s management team and their professional advisors to deliver the emergency work ahead of schedule with minimal disruption

Orion - Rectifying RAAC

Gillian Keegan, Secretary of State for Education visits Orion at St Pauls Catholic School, Esher

Orion Group Project - Thames Ditton

Gillian Keegan, Secretary of State for Education visits Orion at St Pauls Catholic School, Esher

Gillian Keegan, Secretary of State for Education visited Orion at St Paul’s School Esher and was delighted with the works carried out by the Orion team.

 

“Throughout the project Orion have maintained high levels of workmanship and care for our building. From the attention to detail, the quality of protection provided to areas not being worked on, the high levels of H&S and regard for this. Daniel has been extremely thorough throughout the project, maintaining good links and communication. Chris has been extremely professional and shown a lot of flexibility throughout, very helpful and knowledgeable. 

Thank you for orchestrating this work and being able to work around our children and staff returning to school.  We are really pleased with the high-quality finish.”

Head Mistress
St Pauls Catholic School