PROJECT:

Cat A refurbishment of an industrial unit

VALUE:

£200k

LOCATION:

Bilton Way, Luton

DURATION:

8 Weeks

CLIENT:

Quartz Project services Limited

The refurbishment work consisted of:

  • Removal of all tenants fixtures and fittings
  • Utility isolations
  • Safe removal of asbestos ceiling finishes
  • Internal and external cleaning
  • Installation of sanitary ware
  • Floor repairs
  • Improvements to external cladding
  • External brickwork and fencing works
  • Overlaying existing roof finish
  • Redecoration throughout
  • New ceilings in office areas
  • Replacement fire escape doors
  • Installation of new kitchenette
  • New toilets & facilities
  • New floor finishes
  • New UPVC white double gazed windows